+ 1. Ekspluatatsiiya of the car
+ 2. Maintenance
- 3. Engines
   + 3.1. Petrol engines of configuration of R4
   - 3.2. Petrol engine of configuration of VR6
      3.2.1. Technical characteristics
      3.2.2. General information
      3.2.3. Check of a technical condition of the engine
      3.2.4. Removal and engine installation
      3.2.5. Removal and installation of a head of the block of cylinders
      3.2.6. Repair of a head of the block of cylinders
      3.2.7. Pistons and rods
      3.2.8. Cranked shaft
      3.2.9. Replacement of epiploons of a cranked shaft
      3.2.10. Flywheel
      3.2.11. Drive of the gas-distributing mechanism
      3.2.12. Intermediate shaft
      3.2.13. Removal and installation of the oil pallet
      3.2.14. Oil pump
      3.2.15. Water pump
   + 3.3. Diesel engines
+ 4. Cooling system
+ 5. Power supply system
+ 6. Ignition system
+ 7. Coupling
+ 8. Transmission
+ 9. Drive of forward wheels
+ 10. Suspension brackets
+ 11. Steering
+ 12. Brake system
+ 13. Wheels and tires
+ 14. Systems of heating, ventilation and conditioning
+ 15. Electric equipment
+ 16. Body
+ 17. Electric circuits



85288f2d

Repair B3-B4/Passat B3-B4 Volkswagen Passat>> Engines>> Petrol engine of configuration of VR6>> Cranked shaft
Removal of a cranked shaft is carried out in the following order:
– remove the power unit from the car (see подразд. 3.2.4);
– disconnect a transmission from the engine;

Fig. 3.52. Cranked shaft and flywheel: 1–cranked shaft; 2–loose leaves of the shatunny bearing; 3–persistent half rings; 4–loose leaves of the radical bearing; 5–rod; 6–bolt of fastening of a cover of a rod; 7–gear wreath of the sensor of frequency of rotation of a cranked shaft; 8–bolt of fastening of a gear wreath; 9–flywheel; 10-bolt of fastening of a flywheel; 11-adjusting pin of coupling


– unscrew bolts 10 (fig. 3.52) of fastening of a flywheel, having fixed it from a provorachivaniye, and remove a flywheel 9 from a cranked shaft 1;

Fig. 3.53. Drive of auxiliary units: 1–pulley of a cranked shaft; 2–pulley of the water pump; 3–tension roller; 4–mechanism of a tension of a belt of a drive of auxiliary units; 5–generator pulley; 6–pulley of the compressor of the conditioner; 7–pulley of the hydraulic booster of a steering; 8–belt of a drive of auxiliary units


– unscrew a bolt of fastening of a pulley 1 (fig. 3.53) of a cranked shaft and remove a pulley;
– unscrew bolts of fastening of a pulley of the water pump and remove a pulley 2;
– remove chains of a drive of GRM;
– remove a head of the block of cylinders (see подразд. 3.2.5);
– remove the oil pallet;
– remove the oil pump;
– remove pistons with rods in collecting (see подразд. 3.2.7);
– measure axial люфт a cranked shaft with the help щупа (see подразд. 3.1.15) or indicator of hour type. Axial люфт a cranked shaft regulate persistent half rings 3 (see fig. 3.52 ) which are established in the case of the radical bearing No. 5;

Fig. 3.54. Forward and back covers of a cranked shaft, oil pallet: 1–cap of the oil channel; 2–block of cylinders; 3–cover of a drive of GRM; 4–bolt of fastening of a back cover of a cranked shaft; 5–back cover of a cranked shaft; 6–back epiploon of a cranked shaft; 7–laying of the oil pallet; 8–oil pallet; 9–stopper of a masloslivny opening; 10-bolt of fastening of the oil pallet; 11-forward cover of a cranked shaft; 12-bolt of fastening of a forward cover of a cranked shaft; 13-forward epiploon of a cranked shaft


– unscrew bolts 12 (fig. 3.54) of fastening of a forward cover of a cranked shaft and uncover 11 together with a forward epiploon 13;
– unscrew bolts of 4 fastenings of a back cover of a cranked shaft and uncover 5 together with a back epiploon 6;
– mark covers of radical bearings for the subsequent their correct installation;
– unscrew bolts of fastening of covers of radical bearings and remove covers, without taking from them loose leaves;
– remove a cranked shaft;
– remove the top loose leaves of radical bearings (loose leaves of beds of a cranked shaft) and mark them for the subsequent correct installation.
The top loose leaves have a flute for supply of greasing to a cranked shaft.
Fault detection of a cranked shaft is carried out in the sequence described in подразд. 3.1.16.
Controllable parameters are specified in подразд. 3.2.1.
Installation of a cranked shaft is carried out in the following order:
– establish the block of cylinders 2 (see fig. 3.54 ) a case up;
– clear working surfaces of the top loose leaves of radical bearings and grease them with fresh engine oil;
– establish the top persistent half rings 3 (see fig. 3.52 ) the radical bearing No. 5;
– grease all necks of a cranked shaft with 1 fresh engine oil;
– establish a cranked shaft in the block of cylinders;
– establish loose leaves 4 in radical bearings;
– establish persistent half rings 3 in a cover of the radical bearing No. 5;
– establish covers of radical bearings and tighten bolts of fastening of covers the moment of 30 N · m, then tighten them on a corner 180 °;
– turn a cranked shaft manually. It should rotate easily, without breakthroughs;
– check axial люфт a cranked shaft (see подразд. 3.1.15);
– establish pistons with rods assembled;
– establish forward and back covers of a cranked shaft with new epiploons;
– establish a flywheel;
– establish the oil pump;
– put hermetic on surfaces of contact of the block 2 (see fig. 3.54 ) cylinders and the oil pallet 8;
– establish laying 7 oil pallets;
– establish the oil pallet 8 and tighten bolts of the 10th fastening of the oil pallet the moment of 20 N · m cross-wise, beginning from an average part of the pallet;
– execute other operations in sequence, return to removal.